Project
|
Ultimate Client
|
Length of time
|
Images
|
|
|
|
|
|
|
|
Assembly of flexible production line for 4 valve cylinder heads
|
Opel Szentgotthard/Hungary
|
20 weeks
|
-
|
|
|
|
|
|
|
|
Final assembly of 3 production lines for springs incl. testing units
|
Hoesch Hohenlimburg AG, Hamilton/USAGünther
|
26 weeks
|
-
|
|
|
|
|
|
|
Final assembly of a customized plant for manufacturing sectional doors
|
Tore, Altenkirchen
|
4 weeks
|
-
|
|
|
|
|
|
|
Final assembly of a flexible production line for sliding roofs
|
Rockwell Golde, Frankfurt
|
15 weeks
|
-
|
|
|
|
|
|
|
Final assembly of a complete cylinder head manufacturing line incl. all machine tools and automation equipment
|
VW, Polkowice/Poland
|
18 weeks
|
-
|
|
|
|
|
|
|
Final assembly of a complete crankshaft production line incl. all machine tools and automation equipment
|
VW Polkowice/Poland
|
18 weeks
|
-
|
|
|
|
|
|
|
...More references on request. |
|
|
|